Case Study - Hillhead Primary School, Glasgow
Works
commenced in September 2009
Japanese
Knotweed Solutions were appointed to undertake a full site survey
to assess the
extent of the Japanese Knotweed infestation. Digital surveying
equipment was
used to locate the areas of contamination and a full pack of
recommendations
were produced for the Client. The results of this
survey
work qualified that infestation was well established and amounting to
some 2,795 square metres.

The site was to be
remediated for the development of Hillhead Primary School which was being moved
from a nearby site. The existing site contained various small buildings and a
car park away from the infestation which were demolished prior to works. On inspection of
the site drawings it was clear the majority of
infestation was located in the footprint of the proposed building and due to
the construction programme it was recommended that the contaminated material
was removed off-site to licenced landfill and the remainder to be chemically
treated. Our
recommendations were followed and treatment commenced in September 2009
comprising of the following:
After initial
spraying and injecting of herbicide into the root rhizome, JKSL then carried
out removal of all rhizomes from the excavation areas, chasing the root
structure until fully removed. The material was taken to licensed landfill
following stringent methods to avoid any spreading of contaminated material
across the site during excavation.


As a large portion of the root rhizome existed
off-site and in view of persistence of the plant, a vertical root barrier was
installed against the excavated faces preventing any re-growth from migrating
back into the site. Where possible the barrier itself was impregnated with a
residual herbicide to further reduce the chances of re-growth.

Finally, JKSL supervised the demolition contractor removing
the retaining walls in order to prevent cross contamination from occurring and
the Wildlife & Countryside Act (1981) from being compromised. All bricks were
separated of rhizomes and stockpiled for disposal.
The whole
process only took one week which then allowed the development to continue. The new Hillhead Primary School opened in
August 2011.

